Wednesday, January 23, 2008

Roof is finished

They put shingles on the roof last week and most of the electrical and HVAC stuff has been roughed in. We are waiting on windows now. They should be installed next week and then exterior doors. We are in the process of finalizing the stone and brick and the labor for that.

I ran the thermostat wire for the two Rinnai tankless water heaters. We have the thermostats in by each tub/shower and in the kitchen. This weekend I will work on pulling telephone, internet and cable.

We bought the exhaust fan/light units for the 4 bathrooms and the powder room this week plus the vent-a-hood for the kitchen so the vents for all of them can be run. We also need to get the fireplace insert so that can be roughed in.

Always something to do. Speaking of that we ordered the SPA tub on Friday and on Monday the called said it was ready to be picked up. So we need to go get that on Friday. Busy, busy, busy.

No comments: